Eversun's CPL Phase II sulphuric acid plant smoothly handed over – ChinaTexnet.com
Home >> Textile News >> Eversun's CPL Phase II sulphuric acid plant smoothly handed over

Eversun's CPL Phase II sulphuric acid plant smoothly handed over

2023-02-20 08:14:30 CCFGroup

On the morning of February 16th, the sulphuric acid plant of the Eversun Science and Technology's CPL Phase II project was handed over smoothly, indicating that the sulphuric acid plant of the CPL Phase II project has entered the trial production preparation stage. 

 

6381221874707272531667382.jpeg

Company leaders Qu Yaping, Liu Qimin and representatives of various participating units attended the handover ceremony. 

 

Since the start of the sulphuric acid plant of the second phase of the CPL project, Eversun and the construction companies have actively overcome the influence of material shortage, equipment delay, manpower shortage caused by the pandemic, weather and other objective factors, organized regular meetings to analyze the reasons for the delay, focus on the difficult links, and effectively ensure that the key progress nodes.

 

6381221874716653992639198.jpeg

After more than a year of hard work, the sulphuric acid plant of was delivered on schedule.

 

In the next step, Eversun will speed up the tail construction task of the sulphuric acid plant, and scientifically and efficiently do a good job in the feeding and start-up of the plant, so as to lay a solid foundation for the smooth commissioning of the second phase of the CPL project.