2023-05-08 08:48:52 CCFGroup

On April 17, Sichuan Yongying New Materials Project has completed the construction of public works and auxiliary production facilities for most of the first phase of its BDO, biodegradable PBAT and spandex.

The project will build a total of 600kt/year BDO, 500kt/year PBAT and 300kt/year spandex, which will be implemented in three phases.

Production of the first phase includes 300kt/year BDO, 60kt/year PBAT and 60kt/year PTMEG.

The second phase will start a 300kt/year BDO plant.

The third phase of the project will utilize the BDO produced in the first and second stages as raw materials and build downstream PBAT, PTMEG and spandex plants.