Partial installation of Tond BDO project successfully hoisted

2023-11-15 08:44:29 CCFGroup

On November 6, some of the devices in phase I of Xinzhou Tond BDO project, which was built by Shanxi Branch of Thirteen Chemical Engineering Co., Ltd., were hoisted successfully, indicating that the project has achieved important stage results and laid a solid foundation for the smooth progress of the follow-up project.

This hoisting is for BDO I series unit, a total of 7 devices, including butynediol unit, butanediol unit, butanediol distillation unit and freezing station, etc., including 6 sets of more than 40 tons of equipment and 10 sets of other static equipment. Due to the narrow site of the construction site, the main crane of 650 tons of cars and the auxiliary hoisting of 50 tons of cars are used.