Zhongtai Jinhu's 300kt/year BDO project to begin production in 2024
After nearly two years' efforts, Xinjiang Zhongtai Jinhui's BDO project has completed 89.09% of the overall progress, including 100% of the design, 90.53% of the procurement and 83.69% of the construction schedule. Due to the high latitude of the project location and the low winter temperature, the construction progress of the project has slowed down and the start-up time has been delayed until next spring.
In order to ensure that the project is completed as soon as possible, in line with the principle of "early planning, early preparation and early arrangement", the project team of China Chemical Chengda Company, a central enterprise in Sichuan, combines previous years' experience in cold prevention and frost prevention, starting from prevention, all members of the project team try their best to do a good job in cold and freezing prevention, launch a defense war against cold and freezing, ensure that production equipment and facilities survive the winter safely and smoothly, and prepare for the final sprint of the project.
- Top keywords
- Cotton Price
- Cotton Futures Price
- Cotton Futures
- CZCE
- PTA Futures Price
- Chemical Fiber
- Polyester Prices
- Wool price
- PTA Futures
- Shengze Silk
- China
- Yarn Price
- price
- China Textile City
- Fibre Price
- Benzene Price
- Cotton
- Index
- Cotton Index
- PTA
- fabric price
- NYMEX
- Top 10
- textile industry
- Spot Cotton
- Cotton Yarn
- Polyester Price
- Futures
- PTA Price
- cotton yarn price